Fiscal Year 2017 Crack Seal Project
The Fiscal Year 2017 Crack Seal Project will continue the week of March 20th at various locations around the western side of Midland. During the project, traffic will be channeled around the crack seal operation.
Drainage Improvements
City crews will continue making drainage improvements on Canadian Avenue at Spence Drive the week of March 20th. During the project Canadian Ave. will be closed at the intersection of Spence Dr. Traffic will be detoured through adjacent streets throughout the project.
City crews will continue making drainage improvements on Cuthbert Avenue at Marienfeld Street the week of March 20th. During the project Cuthbert Ave. will be closed at the intersection of Marienfeld St. Traffic will be detoured through adjacent streets throughout the project.
City crews will continue making drainage improvements on Lamesa Rd. at Gist Avenue the week of March 20th. During the project Gist Ave. will be closed at the intersection of Lamesa. Traffic will be detoured through adjacent streets throughout the project. Lamesa north and south bound traffic will be maintained throughout the project but lane closures will be utilized. Drivers are asked to use caution in the area.
COMPASS Project on Rhode Island Avenue and South N Street:
The contractor is constructing improvements on Rhode Island Avenue from South Garfield Street to South L Street and on South N Street from West New Jersey Avenue to West Carter Avenue. In this area, the contractor is grading, constructing curb, and paving. Access to businesses may be interrupted during the day.
Beal Parkway Paving Project:
The contractor is working within the newly proposed alignment of Beal Parkway from Audie Court to Blue Haven and Leisure Drive to Thomason Drive. Contractor may set up work day lane closures. Paving operations are complete and paving markings should be installed soon.
Briarwood Avenue Paving Project:
The contractor is currently working along Briarwood Avenue from Avalon Drive to Holiday Hill Road. Traffic is driving in the outer lanes. All affected businesses have access to Briarwood Avenue.
Utility Extension Program on Loop 250 Frontage Road:
The contractor will perform construction along the eastbound Loop 250 frontage road between Tremont Avenue and Henry Koontz Boulevard. There may be temporary lane, road, and intersection closures during construction.