Fiscal Year 2017 Crack Seal Project
The Fiscal Year 2017 Crack Seal Project will continue the
week of April 10th at various locations around the western side of
Midland. During the project, traffic will be channeled around the crack seal
operation.
Drainage Improvements
City crews will continue making drainage improvements on
Cuthbert Avenue at Marienfeld Street the week of April 10th. During
the project Cuthbert Ave. will be closed at the intersection of Marienfeld St.
Traffic will be detoured through adjacent streets throughout the project.
Drainage Improvements
City crews will continue making drainage improvements on
Lamesa Rd. at Gist Avenue the week of April 10th. Gist Ave. will be
closed at intermittent times throughout the remainder of the project at the
intersection of Lamesa. Traffic will be detoured through adjacent streets
throughout the project. Lamesa north and south bound traffic will be maintained
throughout the project but lane closures will be utilized. Drivers are asked to
use caution in the area.
Drainage Improvements
City crews will begin making drainage improvements on
Homestead Boulevard between Mosswood Drive and Ironwood Drive the week of April
10th. Through traffic will be detoured through adjacent streets
throughout the project.
COMPASS
Project on Rhode Island Avenue and South N Street:
The contractor is constructing improvements on Rhode Island
Avenue from South Garfield Street to South L Street and on South N Street from
West New Jersey Avenue to West Carter Avenue. In this area, the contractor is
grading, constructing curb, and paving. Access to businesses may be
interrupted during the day.
Beal
Parkway Paving Project:
The
contractor is working within the newly proposed alignment of Beal Parkway from
Audie Court to Blue Haven and Leisure Drive to Thomason Drive. Contractor
may set up short term lane closures to
place topsoil and seed.
Briarwood
Avenue Paving Project:
The contractor is currently working along Briarwood Avenue
from Avalon Drive to Holiday Hill Road. Traffic is driving in the outer lanes. Paving operations are underway and traffic will be
shifted between the outer lanes to the inner lanes.
Utility Extension Program on Loop 250
Frontage Road:
The
contractor will perform construction along the eastbound Loop 250 frontage road
between Tremont Avenue and Henry Koontz Boulevard. There may be temporary lane,
road, and intersection closures during construction.