Currently in construction: 

  • Cuthbert Ave. from Garfield to “A” (utility work)

Upcoming construction:

  • Cuthbert Ave. from Garfield to “A” (paving)
  • Greentree Blvd. from Holiday Hill to Midland Dr. (paving)
  • Hicks Ave. from Lamesa to Terrell (paving)
  • Taylor Ave. from Lamesa to Mineola (paving)

Background

In 2017, voters approved $100 million in bond funding for the City’s roads and utilities. 60% of the funds will cover the cost of pavement removal and repaving, 24.4% will be devoted to utility line replacement,10.4% will be devoted to Americans with Disabilities (ADA) compliance modifications, and 5.2% will go to engineering costs. The City expects to work on 26 different projects over five years. Check back here to track our progress or sign up to receive updates. 


YEAR 1 PROJECTS

Project Type Design % Complete Construction % Complete
Green Tree Blvd. Paving
Utilities
100%
N/A
50%
N/A
Cuthbert Ave. Paving
Utilities
98%
100%
0
50%
Taylor Ave. Paving
Utilities
100%
100%
20%
100%
Hicks Ave. Paving
Utilities
100%
100%
20%
100%


YEAR 2 PROJECTS

Project Type Design % Complete Construction % Complete
Wood Dr. and Oriole Dr. Paving
Utilities
10%
N/A
0%
N/A
Cuthbert Ave. Paving
Utilities
75%
N/A
0
N/A
Louisiana Ave. Paving
Utilities
0%
30%
0%
0%
Michigan Ave. Paving
Utilities
0%
50%
0%
0%
Texas Ave. Paving
Utilities
0%
0%
0%
0%
Bankhead Hwy. Paving
Utilities
0%
0%
0%
0%
Carter Ave. Paving
Utilities
0%
0%
0%
0%
Bluebird Ln. Paving
Utilities
0%
0%
0%
0%


YEAR 3 PROJECTS

Project Type Design % Complete Construction % Complete
Thomason Dr. Paving
Utilities
0%
0%
0%
0%
Garfield St. Paving
Utilities
0%
0%
0%
0%
A St. (Cuthbert to Indiana) Paving
Utilities
0%
0%
0%
0%


YEAR 4 & 5 PROJECTS

Project Type Design % Complete Construction % Complete
Main St. Paving
Utilities
0%
0%
0%
0%
Solomon Ln. Paving
Utilities
0%
0%
0%
0%
Sunglo St. Paving
Utilities
0%
0%
0%
0%
Sinclair Ave. Paving
Utilities
0%
0%
0%
0%
A St. (Wadley to Scharbauer) Paving
Utilities
0%
0%
0%
0%
New York Ave. Paving
Utilities
0%
0%
0%
0%
Tarlton St. Paving
Utilities
0%
0%
0%
0%
Anetta Dr. Paving
Utilities
0%
0%
0%
0%
Illinois Ave. Paving
Utilities
0%
0%
0%
0%
Whittle Way Paving
Utilities
0%
0%
0%
0%